We are very satisfied indeed with the consistently excellent level of professional service which CQS have provided in the difficult circumstances of this project, ultimately costing over £3m. For a charitable trust such as ours, wholly dependent on grant funding, the pricing of construction work has been of the essence. CQS have been forced by events to revisit the pricing issues several times during the six years to enable the project to be completed within the level of grant- funding secured. To that end Alwyn Williams built up an excellent relationship with the principal of the construction contractor, himself a qualified quantity surveyor, while still questioning his proposed figures, not least for the various extra pieces of work which were required. In particular, at a late stage it was found necessary to renew all the market stalls. The initial price proposed by the contractor was quite unaffordable but by virtue of a detailed analysis of all its cost components was reduced very substantially and the stalls were successfully installed.